newspapers 3488857

News

PRESS RELEASE

Interim Minister of Energy Traicho Traikov visited Chaira pumped-storage hydropower plant to monitor the progress of the plant's repair activities to bring it back to normal operation.

NEK CEO Georgi Dobrev and Chief Technical Director Krassimir Dimitrov presented in detail the results achieved and the challenges overcome.

The 72-hour testing of hydro unit 3, which was repaired last year, are planned for the beginning of April. A specially developed engineering solution was applied to it, which brought hydro unit 2 of the power plant back into operation. It should be noted that that U2 was restored at the end of 2024 and has already operated for 2,757 hours.

Hydro unit 1 will be repaired by the Japanese corporation Toshiba, which is the manufacturer of the original equipment at Chaira PSHPP.

The sustainable solution for hydro unit 4 is its complete replacement, and NEK has a strategy for the successful implementation of the project.

NEK and Toshiba discussed Chaira PSHPP’s restoration

As part of the strategy to gradually bring the Balkans’ largest energy storage facility, Chaira PSHPP, back into operation, the Executive Director of NEK, Georgi Dobrev, the Chief Technical Director, Krasimir Dimitrov, and the Manager of Hydroelektroinvest Enterprise, Denis Beev, held a high-level working meeting at the headquarters of the Japanese corporation Toshiba.

The main focus of the meeting was the repair of Unit 1 of the plant and the coordination of the upcoming activities. Specific steps and follow-up actions were discussed. The meeting confirmed the mutual commitment of the parties’ efforts to the successful restoration of the facility and to ensuring its long-term, reliable, and safe operation.

NEK continues its systematic and focused efforts towards the full restoration of the capacity of Chaira PSHPP, a strategic asset for the energy system of the country and the region.

Toshiba meeting 022026 1

PRESS RELEASE

Successful passage of a high wave through the Arda cascade

A high wave was recorded passing through the three reservoirs of the Arda cascade operated by NEK EAD – Kardzhali, Studen Kladenets and Ivaylovgrad - as a result of heavy rainfall over the past 24 hours under a red alert in southern Bulgaria on 5 February 2026. As of 6 February 2026, we report the successful passing of the high wave, thanks to the continuous operational control carried out by the company's experts.
During the passing high wave, the peak inflow to the first stage of the cascade – the Kardzhali Reservoir – was recorded at 863 m3/sec. In the evening hours of 5 February 2026, two of the four overflow valves of the dam were opened in order to release water flows and reduce its storage volume. With the Kardzhali HPP operating 24 hours a day, the maximum recorded water flow rate through the spillway is 450 m3/sec.
The peak of the total inflow to the Studen Kladenets Reservoir was recorded at 1,870 m3/sec. In the late hours of 5 February 2026, five of the dam's nine overflow valves were opened. With the Studen Kladenets HPP operating 24 hours a day, the maximum overflow water flow rate through the spillway is 1,320 m3/sec.
The peak of the total inflow to the Ivaylovgrad Reservoir, the last stage of the cascade, was recorded at 1,750 m3/sec. The reservoir began to overflow at 23:00 on 5 February 2026, and by 12:00 on 6 February 2026, the overflow water flow rate was 538 m3/sec.
NEK EAD continues to exercise constant operational control over the situation and remains ready to take timely action.

 

Преливане_Студен_кладенец_.png  

 

Преливане_Кърджали_.png

NEK’s Personal Data policy

This site uses cookies. By continuing to browse the site, you agree to NEK’s Personal Data policy